Define Work Center Cost

Explanation

Use this function to define costs related to a work center.

Prerequisites

The work center must have been defined.

System Effects

As a result of this activity, the costs you specify for the work center will be used when calculating costs for parts connected to the work center.

Window

Work Center

Related Window Descriptions

Work Center
Work Center/Cost

Procedure

To perform activity from Work Center/Cost

  1. Open the Work Center window.
  2. Populate or query for the work center.
  3. In the Work Center list, select the work center for which you want to define costs.
  4. Click the Cost tab and create a new record.
  5. In the Cost Set field, enter the cost set for which you want to define the cost.
  6. Specify the cost in the Work Center Cost column.
  7. Create a new record and repeat steps 5 and 6 for each cost you want to enter.
  8. Save.

To perform activity from Work Center Costs

  1. Open the Work Center Costs window.
  2. Create a new record.
  3. Enter the Site and Work Center you want to define cost.
  4. In the Cost Set field, enter the cost set for which you want to define the cost.
  5. Specify the cost in the Work Center Cost, Overhead1 and Overhead2 columns.
  6. Create a new record and repeat steps 3 to 5 for each cost you want to enter.
  7. Save.