One Level Part Cost Calculation

[About Cost Calculation]

[To Costing]

Usage

Use this window to calculate level cost for an inventory part. Level cost is the total cost for this particular level of the part. Total level cost does not include accumulated component material costs. The part cost is calculated for one of the cost sets you use in the system. The calculation will only consider the level cost for the selected part. No costs for any underlying structure will be calculated. However, already calculated costs of the components will be rolled up for one level.

Note: You cannot perform this cost calculation within cost set 1

Activity Diagrams

Cost calculation

Activities

Calculate cost for single part, one level