Usage

Use this tab to view history information logged about the contract change order. This information can be used to monitor the development of the change order, for example it is possible to view status changes, when the change order was approved or if externally rejected along with the reject reason. The expected, requested and agreed values for the changes orders are also listed. The information on this tab is inserted automatically and effects nothing else in the system.

Activity Diagrams

Register Contract Change Order
Analyze Contract Change Order
Approve Contract Change Order
Plan and Implement Contract Change Order
Finalize Contract Change Order

Activities

View Contract Change Order History