Define Planned Hours and Costs on Design Object

Explanation

This activity is used to enter estimated cost and hours on the design object.

If the connection to IFS/Project exists, the values you enter here will be reported automatically on a project activity. Further, the total scope for planned cost and hours is calculated and updated on the project activity. For more information refer to the about description for Project Management in IFS/Asset Design.

If the design object is connected to a project, the cost fields will be updated with a currency code. This will be the default currency code of the company defined for the project.

Prerequisites

A project and an activity needs to be defined on the design object. This will enable the automatic transfer of planned hours and costs from the design object to a project activity.

System Effects

If the design object is connected to a project and project activity, the planned values are updated on the project activity.

Window

Design Object
Project Connections

Related Window Descriptions

Design Object
Project Connections
Planned Cost and Hours

Procedure

Use this procedure to enter the planned hours and costs on the design object using the Design Object window.

  1. Open the Design Object window.
  2. Search for the object on which you wish to report planned hours and costs.
  3. Click the Project tab.
  4. In the Cost Elements table, click New.
  5. In the Cost Element field, enter the cost element, or use the List of Values to select one, for which you want to report planned hours or costs.
  6. In the Planned Cost field, enter the planned cost or hours for the selected object.
  7. Click Save.

Use this procedure to add a project cost element to gather planned cost on the design object (apart from the cost elements to gather planned material, work and miscellaneous cost):

  1. Open the Project Connections window and select the object for which you want to add a project cost element.
  2. Right click on the object and select Planned Cost and Hours. The Planned Cost and Hours dialog box opens.
  3. Click New.
  4. In the Cost Element field, enter a cost element, or use the List of Values to select one, to add to the design object.
  5. In the Planned Cost field, enter a planned cost that you want to associate with the cost element you just entered for the selected design object.
  6. In the Planned Hours field, enter planned hours that you want to associate with the cost element you just entered for the selected design object.
  7. Click OK.